Pattern search method for accelerating Stope boundary optimization problem in underground mining operations
Authors:
- 7 June 2021
- journal article
- research article
- Published by Taylor & Francis in Engineering Optimization
- Vol. 54 (5) , 881-893
Abstract
The Stope Boundary Optimization (SBO) problem refers to the layout design of production areas (stopes) in an underground mining operation. It falls within the domain of strategic mine planning and a model that addresses this problem aims to maximize profitability, offers optimal management of mineral resources and facilitates decision making around capital investments. The SBO problem is computationally complex and a method that offers solution within a reasonable computation time does not exist. In this article, a combination of a new greedy algorithm and a pattern search technique with an integer programming model is proposed. An implementation of the proposed method on three realistic case studies confirms its efficiency in generating robust solutions with a better optimality gap and considerably less computational effort.Keywords
This publication has 14 references indexed in Scilit:
- A 3D approximate hybrid algorithm for stope boundary optimizationComputers & Operations Research, 2020
- Stope boundary optimization: A mathematical model and efficient heuristicsResources Policy, 2019
- Underground mine planning: stope layout optimisation under grade uncertainty using genetic algorithmsInternational Journal of Mining, Reclamation and Environment, 2018
- Implementation and comparison of four stope boundary optimization algorithms in an existing underground mineInternational Journal of Mining, Reclamation and Environment, 2017
- Stope optimization with vertical convexity constraintsOptimization and Engineering, 2016
- Designing an optimal stope layout for underground mining based on a heuristic algorithmInternational Journal of Mining Science and Technology, 2015
- A heuristic approach to optimal design of an underground mine stope layoutApplied Soft Computing, 2015
- Underground stope optimization with network flow methodComputers & Geosciences, 2013
- Simultaneous optimisation of stope layouts and long term production schedulesMining Technology: Transactions of the Institutions of Mining and Metallurgy, 2011
- A new algorithm for stope boundary optimizationJournal of Coal Science and Engineering (China), 2010