Relocation Scheduling in a Two-Machine Flow Shop with Resource Recycling Operations
Open Access
- 29 June 2021
- journal article
- research article
- Published by MDPI AG in Mathematics
- Vol. 9 (13) , 1527
Abstract
This paper considers a variant of the relocation problem, which is formulated from an urban renewal project. There is a set of jobs to be processed in a two-machine flow shop subject to a given initial resource level. Each job consumes some units of the resource to start its processing on machine 1 and will return some amount of the resource when it is completed on machine 2. The amount of resource released by a job is not necessarily equal to the amount of resource acquired by the job for starting the process. Subject to the resource constraint, the problem is to find a feasible schedule whose makespan is minimum. In this paper, we first prove the NP-hardness of two special cases. Two heuristic algorithms with different processing characteristics, permutation and non-permutation, are designed to construct feasible schedules. Ant colony optimization (ACO) algorithms are also proposed to produce approximate solutions. We design and conduct computational experiments to appraise the performances of the proposed algorithms.Keywords
Funding Information
- Ministry of Science and Technology, Taiwan (MOST 109-2923-H-009-001-MY3)
This publication has 29 references indexed in Scilit:
- Resource-constrained flowshop scheduling with separate resource recycling operationsComputers & Operations Research, 2010
- Johnson’s rule, composite jobs and the relocation problemEuropean Journal of Operational Research, 2009
- Maximizing the reward in the relocation problem with generalized due datesInternational Journal of Production Economics, 2008
- On the relocation problem with a second working crew for resource recyclingInternational Journal of Systems Science, 2006
- Resource-constrained project scheduling: Notation, classification, models, and methodsEuropean Journal of Operational Research, 1999
- Polynomial algorithms for single machine scheduling problems with financial constraintsOperations Research Letters, 1997
- Some results of the relocation problems with processing times and deadlinesInternational Journal of Computer Mathematics, 1991
- Relocation problems are hardInternational Journal of Computer Mathematics, 1988
- Scheduling Problems With Generalized Due DatesIIE Transactions, 1986
- Optimal two‐ and three‐stage production schedules with setup times includedNaval Research Logistics Quarterly, 1954