During the first quarter of FY20, work focused on implementing a subcontract with Penn State University to collaborate on the project. Significant delays prevented the subcontract from being placed until the end of December. As a result only limited progress was made on the project. Required equipment was researched and ordered during the first quarter but will not be delivered until the middle of the second quarter of FY20. Delays are not expected to adversely impact the schedule of the project.