Analysis of Contracts to Build Energy Infrastructures to Optimize the OPEX
Open Access
- 3 September 2020
- journal article
- research article
- Published by MDPI AG in Sustainability
- Vol. 12 (17) , 7232
Abstract
The employer (owner) of the project wants to obtain the maximum profit for the money invested and the consultant (contractor) will try to give less for that money. The regulation of their relationship is based on the contractual agreement, which in the energy sector is mainly based on the engineering, procurement, and construction (EPC) model. The objective of this work was to evaluate which factors should be included in the drafting of contracts, to minimize problems between the parties, and thus minimize execution costs and optimize operation and maintenance costs. Information and data on the integration of operability and maintainability criteria in contracts for 158 projects, with a total contract value of close to €40,000M, were analyzed. Several of those projects corresponded to wind, solar, and hydroelectric plants. The information collected the perception of the agents involved, and was classified according to the experience of the agents consulted in the operation and maintenance areas. Finally, the proposed criteria were prioritized. In general, the owner is willing to introduce these criteria in his contracts if they reduce the operation and maintenance cost by around 1–5%, while the contractor is interested in increasing his probability to be selected by 1–3%.Keywords
This publication has 41 references indexed in Scilit:
- Heuristic approach for risk assessment modeling: EPCCM application (Engineer Procure Construct Contract Management)Alexandria Engineering Journal, 2012
- Study on Cost Management under EPC General Contracting ModelAdvanced Materials Research, 2011
- The coalescence between synergies and conflicts of interest in a top consultancy firm: an analysis of the implications for consultants' attitudes and behavioursHuman Resource Management Journal, 2010
- 4-E (Energy, Exergy, Environment, and Economic) analysis of solar thermal aided coal-fired power plantsEnergy for Sustainable Development, 2010
- Modelo de aprendizaje para la selección de un proyecto diseño-construcción (llave en mano) en el sector públicoRevista ingeniería de construcción, 2010
- Factors affecting the cost of capture for Australian lignite coal fired power plantsEnergy Procedia, 2009
- Managing conflict in construction megaprojects: Leadership and third‐party principlesConflict Resolution Quarterly, 2008
- Supply risk management vs supplier selection to manage the supply risk in the EPC supply chainManagement Research News, 2008
- Stop chasing the Front End process — management of the early phases in product development projectsInternational Journal of Project Management, 2002
- The need for new paradigms for complex projectsInternational Journal of Project Management, 1999