Production Equations for Unsteady-State Construction Processes
- 1 March 2007
- journal article
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 133 (3) , 254-261
Abstract
The production equation called Little’s law has been applied to construction data recently. However, Little’s law was derived for steady-state conditions assuming constant input and output rates and long production runs. Production in construction is inherently temporary, and learning curves and environmental influences often render input and output rates unequal and nonlinear. Starting with a conservation of mass formulation, general equations for work-in-process and cycle time for unsteady-state conditions and limited run production are developed. The motivation behind these equations is to explain common trends in production variables seen on construction projects. Previous studies have shown that when output from a construction production system is drastically increased, a significant upward impact is also seen on cycle time and work-in-process, and this work provides underlying theory and equations to explain these trends. Cycle time and work-in-process equations are presented as functions of time an...Keywords
This publication has 9 references indexed in Scilit:
- Role of Inventory Buffers in Construction Labor PerformanceJournal of Construction Engineering and Management, 2005
- Production System Loading–Cycle Time Relationship in Residential ConstructionJournal of Construction Engineering and Management, 2005
- Improving Labor Flow Reliability for Better Productivity as Lean Construction PrincipleJournal of Construction Engineering and Management, 2003
- A Mesoscopic Approach to the Simulation of Semiconductor Supply ChainsSIMULATION, 2003
- Reducing Variability to Improve Performance as a Lean Construction PrincipleJournal of Construction Engineering and Management, 2002
- Role of the Fabricator in Labor ProductivityJournal of Construction Engineering and Management, 2000
- Parade Game: Impact of Work Flow Variability on Trade PerformanceJournal of Construction Engineering and Management, 1999
- Loss of Labor Productivity due to Delivery Methods and WeatherJournal of Construction Engineering and Management, 1999
- Pull-Driven Scheduling for Pipe-Spool Installation: Simulation of Lean Construction TechniqueJournal of Construction Engineering and Management, 1998