What happens when two amorphous core distribution transformers are energized in parallel, and how does the inrush transient in one unit provoke a sympathetic response in the other? This research addressed both questions through controlled laboratory measurements on two 250 kVA, 11/0.433 kV amorphous metal distribution transformers connected to a common 11 kV bus. Five switching configurations were examined: individual energization of each transformer, simultaneous parallel energization, sequential parallel energization with a 200 ms stagger, and sequential energization under partial resistive load. A 16-bit, 10 kS/s data acquisition platform captured instantaneous phase currents at the primary terminals, and a residual flux estimation procedure preceded each test. Peak inrush magnitudes reached 12.68 A (5.07 per-unit) during simultaneous parallel switching, exceeding single-unit peaks by 49.8%. Sympathetic interaction currents in the already-connected transformer peaked at 5.73 A and persisted for 1.87 s, roughly three times the single-unit decay constant. Staggering the closure by 200 ms lowered the sympathetic peak to 3.89 A, a 32.1% reduction, while partial loading before the second unit joined cut it to 2.14 A. Waveform analysis showed that the sympathetic current contained a pronounced second-harmonic component, reaching 38.4% of the peak, which may interfere with harmonic-restrained differential protection. Results point to sequential energization under load as the preferred switching strategy for parallel amorphous core transformers on distribution feeders. These outcomes hold practical value for utility protection engineers designing relay settings and switching procedures in networks that increasingly deploy amorphous core units for their lower no-load losses.