The aim of this study is to assess the potential settlements of the crest of the Vedi Dam based on field observations during the construction period. The results indicate that dam settlements follow an asymptotically decreasing trend over time. After 1000–1200 days from the placement of a layer, the settlements amount to approximately 5% of the total construction-period settlements, effectively tapering off. Based on prior findings, it is concluded that the expected maximum settlements during the construction period, even under a linear (upper-bound) forecast, will total 128.5 cm. Therefore, by the end of construction, the remaining settlements are estimated to be about 6 cm, a value that can be considered insignificant. Field monitoring results from inclinometers show classical compliance with theoretical studies in the field. This suggests high construction quality of the dam embankment and indicates no expected anomalies in settlement during the operational period. The dam embankment was constructed slowly-for about six years -which contributed to significant self-compaction of the dam body. It can be concluded that actual operational settlements will not exceed those calculated using the Lawton-Lester formula and will remain within a limit of 81 cm.