Simulation-based approach to quantify the impact of stochastic time-window constraints on construction schedules and budgets for remote cold regions
- 24 September 2026
- journal article
- Published by Emerald Publishing in Engineering, Construction and Architectural Management
- p. 1-28
Abstract
Purpose: This study addresses the planning and scheduling challenges of construction projects in environments with strict climate-induced time constraints, such as winter road availability and temperature-dependent work windows. The research focuses on assessing risks to project timelines and budgets by analyzing historical meteorological and winter road data to model uncertainties in the start and end dates of these critical time windows. Design/methodology/approach: The project schedule is developed based on technological and precedence relationships, while adhering to environmental constraints. Risks are evaluated solely in terms of time-window variability, excluding other uncertainties such as crew productivity or activity duration changes. Deterministic project baselines are established using averaged historical data for time-window boundaries as the base case. A Monte Carlo simulation then samples open and close dates from fitted probability distributions to quantify schedule and budget risks relative to this baseline. Findings: Monte Carlo simulation of stochastic winter-road and thawing time windows for the Northwest Territories bridge case study shows an 84.78% probability of completing the project within the 654-day target schedule and a 21.08% probability of staying under the $28.5 million target budget. The joint probability of meeting both targets is 20.72%. Shorter winter-road windows at project start substantially increase total costs, demonstrating that climate variability significantly affects sequencing, resource allocation and overall project risk in remote cold regions. Originality/value: This research introduces a novel simulation-based framework for quantifying climate-related risks in cold-region construction, extending prior time-window methods with stochastic modelling. It offers a foundational risk-informed approach, with the potential to incorporate additional uncertainties like productivity fluctuations or alternative methods in future studies.Keywords
Funding Information
- Natural Sciences and Engineering Research Council of Canada (RGPIN-2023-04398)
This publication has 31 references indexed in Scilit:
- Risk-integrated scheduling for commercial building construction: a BIM and Monte Carlo simulation approachAsian Journal of Civil Engineering, 2025
- Truck Scheduling: A Case Study in the Automotive SectorInternational Journal of Applied and Computational Mathematics, 2024
- Critical chain based Proactive-Reactive scheduling for Resource-Constrained project scheduling under uncertaintyExpert Systems with Applications, 2022
- Application of critical path method to stochastic processes with historical operation dataChemical Engineering Research and Design, 2019
- Implications of projected climate change on winter road systems in Ontario’s Far North, CanadaClimatic Change, 2018
- Non-parametric weather generator for modelling construction operations: Comparison with the parametric approach and evaluation of construction-based impactsAutomation in Construction, 2017
- Trends in the seasonal length and opening dates of a winter road in the western James Bay region, Ontario, CanadaTheoretical and Applied Climatology, 2016
- Permafrost thermal state in the polar Northern Hemisphere during the international polar year 2007–2009: a synthesisPermafrost and Periglacial Processes, 2010
- Extending the RCPSP for modeling and solving disruption management problemsApplied Intelligence, 2008
- Effect of hot weather on modulus of rupture and splitting tensile strength of concreteCement and Concrete Research, 1985