Rapid Pre-construction Forecasting of Schedule Overruns: A Machine Learning Regression Approach
Authors:
- Caesar Abi ShdidCSCaesar Abi Shdid
- Rita AwwadRARita Awwad
- Joshua NasrJNJoshua Nasr
Open Access
- 5 November 2026
- journal article
- Published by Bentham Science Publishers Ltd. in The Open Construction & Building Technology Journal
- Vol. 20 (1)
Abstract
Introduction/Objective: This study developed and validated a parsimonious machine-learning regression model that estimates schedule overruns for building construction projects prior to project start. Methods: Using a dataset of 60 completed building projects in Lebanon, each with 11 pre-project predictors, an XGBoost regression model was trained and tested on an independent dataset, with repeated cross-validation and hyperparameter tuning. Results: Averaged over repeated randomized train/test partitions, the trained and tuned model achieved an R 2 = 79.6% (adjusted R 2 = 74.3%), a mean absolute error of 4.36 ± 0.48 percentage points (95% CI: 3.42–5.30), and a median coverage near the nominal 90% for empirical prediction intervals. Discussion: The regression-based approach extends existing delay-risk assessment by estimating delay magnitude rather than only the risk class, while factor-importance analysis identified owner/client performance, legal/permit issues, design quality, and project manager experience as the major drivers of delay. Conclusion: The model provides a practical decision-support tool for project managers to estimate the expected magnitude of delay and its uncertainty before construction initiation, requiring only eleven readily obtainable pre-project inputs.Keywords
This publication has 38 references indexed in Scilit:
- Predicting construction delay risks in Saudi Arabian projects: A comparative analysis of CatBoost, XGBoost, and LGBMExpert Systems with Applications, 2024
- Study the delays and conflicts for construction projects and their mutual relationship: A reviewAin Shams Engineering Journal, 2022
- Utilizing Computer Vision and Fuzzy Inference to Evaluate Level of Collision Safety for Workers and Equipment in a Dynamic EnvironmentJournal of Construction Engineering and Management, 2020
- Next-Generation Machine Learning with Spark2020
- Machine Learning Algorithms for Construction Projects Delay Risk PredictionJournal of Construction Engineering and Management, 2020
- Large-Scale Cortical Networks for Hierarchical Prediction and Prediction Error in the Primate BrainNeuron, 2018
- Risk Analysis in Construction Project - Chosen MethodsProcedia Engineering, 2015
- Project Management with Dynamic Scheduling2013
- Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case studyInternational Journal of Project Management, 2003
- Project Management in Construction: Software Use and Research DirectionsJournal of Construction Engineering and Management, 2001