Alternative for Quantifying Field-Overhead Damages
- 1 October 2007
- journal article
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 133 (10) , 736-742
Abstract
The context of delays significantly affects delay responsibility. Among other things, recoverable damages for a delay should be related to the timing of the corresponding delay and its effect on indirect costs. This paper presents an alternative and integrated approach for quantifying and apportioning delay responsibility. It considers the context of a delay in terms of its timing and the degree of suspension during the course of a project. The proposed approach allocates project-site overhead costs onto schedule activities. It then helps track site overhead damages in a “real-time” manner while schedule-window analysis is employed to analyze the delay. A case study is used to illustrate its application. Results infer that the conventional daily overhead rate-based method can cause double payments because conventional recovery possibly covers parts of field overhead already paid from the original contract. This new approach also enables the application of the comparative negligence doctrine when concurren...Keywords
This publication has 8 references indexed in Scilit:
- Avoiding and Minimizing Construction Delay Claim Disputes in Relational ContractingJournal of Professional Issues in Engineering Education and Practice, 2006
- Daily Windows Delay AnalysisJournal of Construction Engineering and Management, 2005
- United Kingdom Construction Claims: Views of ProfessionalsJournal of Construction Engineering and Management, 2004
- Unabsorbed Overhead and the Eichleay FormulaJournal of Professional Issues in Engineering Education and Practice, 2003
- Indirect Cost Categorization and Allocation by Construction ContractorsJournal of Architectural Engineering, 1999
- Window Analyses of Compensable DelaysJournal of Construction Engineering and Management, 1999
- FEATURE: Thinking Ahead with Forward PricingJournal of Management in Engineering, 1996
- Concurrent Delays in Construction ProjectsJournal of Construction Engineering and Management, 1987