Minimizing the Duration of Repetitive Construction Processes with Work Continuity Constraints
Open Access
- 6 March 2019
- journal article
- research article
- Published by MDPI AG in Computation
- Vol. 7 (1) , 14
Abstract
This study adopts the flow shop concept used in industrial production to schedule repetitive non-linear construction projects, where specialized groups of workers execute processes in work zones (buildings) in a predefined order common to all groups. This problem is characteristic of construction projects that involve erecting multiple buildings. As the duration of the project heavily depends upon the sequence of the work zones, this study aims at providing a model and a practical approach for finding the optimal solution that assures the shortest duration of the project, allows the contractor to complete particular work zones (buildings) as soon as possible (without idle time), and conforms to a predefined sequence of work zone completion. This last constraint may arise from the client’s requirements or physical conditions of the project and has not been addressed by existing scheduling methods. Reducing the duration of the entire project brings the benefit of lower indirect costs and, if accompanied by a reduced duration of completing particular buildings (i.e., work zones), may also provide the opportunity to sell project deliverables sooner, thus improving the economic efficiency of the project. In search of optimal schedules, the authors apply the algorithms of Minimum Hamiltonian Cycle/Asymmetric Traveling Salesman Problem (ATSP).Keywords
Funding Information
- Ministry of Science and Higher Education in Poland (S/63 /2018)
This publication has 39 references indexed in Scilit:
- Flowshop scheduling of construction processes with uncertain parametersArchives of Civil and Mechanical Engineering, 2019
- Minimizing duration and crew work interruptions of repetitive construction projectsAutomation in Construction, 2018
- On the exact solution of the no-wait flow shop problem with due date constraintsComputers & Operations Research, 2017
- A new Nawaz–Enscore–Ham-based heuristic for permutation flow-shop problems with bicriteria of makespan and machine idle timeEngineering Optimization, 2016
- A genetic algorithm-based method for scheduling repetitive construction projectsAutomation in Construction, 2009
- The flow shop problem with no-idle constraints: A review and approximationEuropean Journal of Operational Research, 2009
- Heuristic for no-wait flow shops with makespan minimizationInternational Journal of Production Research, 2008
- System development for non-unit based repetitive project schedulingAutomation in Construction, 2005
- A travelling salesman approach to solve the F/no-idle/Cmax problemEuropean Journal of Operational Research, 2005
- Comparison of Linear Scheduling Model and Repetitive Scheduling MethodJournal of Construction Engineering and Management, 2003