Resource-loaded piping spool fabrication scheduling: material-supply-driven optimization
Authors:
Open Access
- 11 April 2017
- journal article
- research article
- Published by Springer Nature in Visualization in Engineering
- Vol. 5 (1) , 1-14
Abstract
Background: As offsite prefabrication and modular construction continue to gain momentum into the future, material supply chain becomes increasingly complex for modern construction projects. Pre-engineered material supply presents itself as a driver for planning crew installation operations on site that involve skilled labor and heavy equipment. Methods: This paper proposes a framework for implementing the material-supply-driven project planning and control optimization approach to deal with material delays that take place at the piping spool fabrication shop. Design drawings, contract deadlines, resources availability and material supply patterns are extracted from a real oil and gas expansion project to validate the proposed implementation methodology. Results: An interactive Gantt chart with information on activity start time, duration, and allocated resources is generated to visualize the optimization outcome. In connection with the resource-constrained schedule, material supply-demand patterns over project duration are also visualized. Conclusions: These two forms of visualizations provide insightful decision-making support in coping with material delay while fulfilling project objectives. Ultimately, material-supply driven crew job schedules in correspondence with particular objectives and implementation strategies can be generated, ready to guide project execution.Keywords
Funding Information
- Natural Sciences and Engineering Research Council of Canada (CRDPJ 414616-11)
- JV Driver Projects Ltd. (CRDPJ 414616-11)
This publication has 25 references indexed in Scilit:
- Automatically tracking engineered components through shipping and receiving processes with passive identification technologiesAutomation in Construction, 2012
- Project-driven supply chains: integrating safety-stock and crashing decisions for recurrent projectsAnnals of Operations Research, 2012
- Optimizing linear project scheduling with multi-skilled crewsAutomation in Construction, 2012
- The Concept and Development of Supply Chain Management in the UK Construction Industry2009
- Early Contractor Involvement in Design and Its Impact on Construction Schedule PerformanceJournal of Management in Engineering, 2009
- Introduction2008
- Coordination mechanisms for construction supply chain management in the Internet environmentInternational Journal of Project Management, 2007
- Developing a Resource Supply Chain Planning System for Construction ProjectsJournal of Construction Engineering and Management, 2006
- The construction industry as a loosely coupled system: implications for productivity and innovationConstruction Management and Economics, 2002
- Model-based computing: Developing flexible machine control softwareArtificial Intelligence, 1999