Analysis of Adverse Weather for Excusable Delays
- 1 December 2010
- journal article
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 136 (12) , 1258-1267
Abstract
Severe weather conditions can be disruptive to construction. Contractors typically obtain time extensions for weather days beyond normal conditions. However, contracting parties often dispute the extent of weather-related time extensions. Typical industry contracts may overlook many important points that can provide an acceptable resolution. This paper classifies seven factors causing discrepancies in analysis of adverse weather for time extensions; namely, the definition of normal weather, weather thresholds, type of work, lingering days, criteria for lost days, lost days equivalent due to lost productivity, and work days lost versus calendar days lost. An analysis of an actual weather-caused delay claim illustrates the impacts of those factors on the outcomes of the analysis. A contract should define anticipated weather delay days and their lingering days and provide threshold values for weather parameters to differentiate between predictable and unpredictable severe weather. The contract should clearly...Keywords
This publication has 19 references indexed in Scilit:
- Causes of Delay in Building Construction Projects in EgyptJournal of Construction Engineering and Management, 2008
- Relationship between Organizational Sizes and Contractors’ Risk Pricing Behaviors for Weather Risk under Different Project Values and DurationsJournal of Construction Engineering and Management, 2008
- Delay Analysis under Multiple Baseline UpdatesJournal of Construction Engineering and Management, 2008
- Impact of Rainfall on the Productivity of Highway ConstructionJournal of Construction Engineering and Management, 2001
- Generic Methodology for Analyzing Delay ClaimsJournal of Construction Engineering and Management, 1999
- Loss of Labor Productivity due to Delivery Methods and WeatherJournal of Construction Engineering and Management, 1999
- Claims for extensions of time in civil engineering projectsConstruction Management and Economics, 1998
- Estimating weather impact on the duration of construction activitiesCanadian Journal of Civil Engineering, 1997
- Construction Claims and Disputes: Causes and Cost/Time OverrunsJournal of Construction Engineering and Management, 1994
- Climatic Effects on ConstructionJournal of Construction Engineering and Management, 1985