Abstract
The Deep Mixing Method (DMM) was selected at the LPV 111 Project to improve the adverse geotechnical properties of the foundation soil and consequently stabilize and support the burden of the new levee. DMM was executed with two different technologies: Trevi Turbo Mix (TTM) and Contrivance Innovation Cement Mixing Columns (CI-CMC). DMM entails the in-situ mixing of soil with an established amount of cement binder. A preliminary laboratory program (Bench-Scale Test, 4 phases) and a field test program (Validation Tests, 5+ phases) were conducted to estimate the appropriate binder type and dosage and the most effective equipment configuration. The outcome of the various phases guided the design of the grout mixes and the installation parameters for the several field test zones that were performed prior to and during production mixing at LPV 111. Comparative analyses and interpretations between the various lab and field stages, along with accumulated information about soil properties and QC results, allowed fine-tuning of the production parameters throughout almost the entire project. The required quality control/quality assurance (QC/QA) testing program for the LPV 111 project was massive: over 500 core holes (3% of total elements) were drilled and over 5,000 specimens were tested to determine unconfined compressive strength and uniformity of the DMM elements. All data were recorded, analyzed, and interpreted to provide a high quality end product, to demonstrate compliance with the project specifications and to provide a valuable reference for future deep mixing projects.