Mohsen Bagheri
Current Organizations / Institutes
The organizations/institutes from the scholar's latest article
Mohsen Bagheri has a total of 2 co-authors. Here are the top co-authors by number of shared publications:
- Mohammad Taghi Assadi
Department of Industrial Engineering, Faculty of Industrial Engineering and Management, Sadjad University, Mashhad, Iran
1 shared publication - Niloofar Nikoofal Sahl Abadi
Department of Industrial Engineering Sadjad University of Technology Mashhad Iran
1 shared publication
Latest Publications
- 12 January 2016
- Published by Wiley in International Transactions in Operational Research
- Vol. 25 (6) , 2009-2030
Multiobjective model for solving resource‐leveling problem with discounted cash flows
Nowadays, executers are struggling to improve the economic and scheduling situation of projects. Construction scheduling techniques often produce schedules that cause undesirable resource fluctuations that are inefficient and costly to implement on site. The objective of the resource‐leveling problem is to reduce resource fluctuation related costs (hiring and firing costs) without violating the project deadline. In this article, minimizing the discounted costs of resource fluctuations and minimizing the project makespan are considered in a multiobjective model. The problem is formulated as an integer nonlinear programming model, and since the optimization problem is NP‐hard, we propose multiobjective evolutionary algorithms, namely nondominated sorting genetic algorithm‐II (NSGA‐II), strength Pareto evolutionary algorithm‐II (SPEA‐II), and multiobjective particle swarm optimization (MOPSO) to solve our suggested model. To evaluate the performance of the algorithms, experimental performance analysis on various instances is presented. Furthermore, in order to study the performance of these algorithms, three criteria are proposed and compared with each other to demonstrate the strengths of each applied algorithm. To validate the results obtained for the suggested model, we compared the results of the first objective function with a well‐tuned genetic algorithm and differential algorithm, and we also compared the makespan results with one of the popular algorithms for the resource constraints project scheduling problem. Finally, we can observe that the NSGA‐II algorithm presents better solutions than the other two algorithms on average.
- 12 January 2016
- Published by Wiley in International Transactions in Operational Research
- Vol. 25 (6) , 2009-2030
Multiobjective model for solving resource‐leveling problem with discounted cash flows
Nowadays, executers are struggling to improve the economic and scheduling situation of projects. Construction scheduling techniques often produce schedules that cause undesirable resource fluctuations that are inefficient and costly to implement on site. The objective of the resource‐leveling problem is to reduce resource fluctuation related costs (hiring and firing costs) without violating the project deadline. In this article, minimizing the discounted costs of resource fluctuations and minimizing the project makespan are considered in a multiobjective model. The problem is formulated as an integer nonlinear programming model, and since the optimization problem is NP‐hard, we propose multiobjective evolutionary algorithms, namely nondominated sorting genetic algorithm‐II (NSGA‐II), strength Pareto evolutionary algorithm‐II (SPEA‐II), and multiobjective particle swarm optimization (MOPSO) to solve our suggested model. To evaluate the performance of the algorithms, experimental performance analysis on various instances is presented. Furthermore, in order to study the performance of these algorithms, three criteria are proposed and compared with each other to demonstrate the strengths of each applied algorithm. To validate the results obtained for the suggested model, we compared the results of the first objective function with a well‐tuned genetic algorithm and differential algorithm, and we also compared the makespan results with one of the popular algorithms for the resource constraints project scheduling problem. Finally, we can observe that the NSGA‐II algorithm presents better solutions than the other two algorithms on average.