Multiobjective model for solving resource‐leveling problem with discounted cash flows
- 12 January 2016
- journal article
- research article
- Published by Wiley in International Transactions in Operational Research
- Vol. 25 (6) , 2009-2030
Abstract
Nowadays, executers are struggling to improve the economic and scheduling situation of projects. Construction scheduling techniques often produce schedules that cause undesirable resource fluctuations that are inefficient and costly to implement on site. The objective of the resource‐leveling problem is to reduce resource fluctuation related costs (hiring and firing costs) without violating the project deadline. In this article, minimizing the discounted costs of resource fluctuations and minimizing the project makespan are considered in a multiobjective model. The problem is formulated as an integer nonlinear programming model, and since the optimization problem is NP‐hard, we propose multiobjective evolutionary algorithms, namely nondominated sorting genetic algorithm‐II (NSGA‐II), strength Pareto evolutionary algorithm‐II (SPEA‐II), and multiobjective particle swarm optimization (MOPSO) to solve our suggested model. To evaluate the performance of the algorithms, experimental performance analysis on various instances is presented. Furthermore, in order to study the performance of these algorithms, three criteria are proposed and compared with each other to demonstrate the strengths of each applied algorithm. To validate the results obtained for the suggested model, we compared the results of the first objective function with a well‐tuned genetic algorithm and differential algorithm, and we also compared the makespan results with one of the popular algorithms for the resource constraints project scheduling problem. Finally, we can observe that the NSGA‐II algorithm presents better solutions than the other two algorithms on average.Keywords
This publication has 38 references indexed in Scilit:
- Hybrid meta-heuristic methods for the multi-resource leveling problem with activity splittingAutomation in Construction, 2012
- Resource leveling scheduling by an ant colony-based modelJournal of Industrial Engineering International, 2012
- A new hybrid multi-objective Pareto archive PSO algorithm for a bi-objective job shop scheduling problemExpert Systems with Applications, 2011
- On the Use of Net Present Value in Investment Capacity Planning ModelsIndustrial & Engineering Chemistry Research, 2008
- An Optimization Model for Stochastic Project Networks with Cash FlowsComputational Management Science, 2006
- An optimal construction resource leveling scheduling simulation modelCanadian Journal of Civil Engineering, 2002
- Optimal resource leveling of multi-resource projectsComputers & Industrial Engineering, 1996
- Using discounted cash flow heuristics to improve project net present valveJournal of Operations Management, 1996
- Muiltiobjective Optimization Using Nondominated Sorting in Genetic AlgorithmsEvolutionary Computation, 1994
- Taguchi techniques for quality engineering, Philip J. Ross, Mcgraw‐hill book company, 1988Quality and Reliability Engineering International, 1989