PBPrince Boateng

Prince Boateng

*This is an algorithmically generated author record based on publicly available information.

Current Organizations / Institutes

The organizations/institutes from the scholar's latest article

Previous Organizations / Institutes

The organizations / institutes from the scholar's other articles in the past ten years


Prince Boateng has a total of 19 co-authors. Here are the top co-authors by number of shared publications:


Latest Publications

  • Socio-ecological risks management dynamic simulation in megaproject development of the Edinburgh Tram Network

    by Prince Boateng, Temitope Omotayo, Temidayo Osunsanmi, Damilola Ekundayo

    Purpose: The inherent risks and their interactive impacts in megaproject development have been found in numerous cases worldwide. Although risk management standards have been recommended for the best practice in engineering construction projects, there is still a lack of systematic approaches to describing the interactions. Interactions such as social, technical, economic, ecological and political (STEEP) risks have complex and dynamic implications for megaproject construction. For a better understanding and effective management of megaprojects such as the Edinburgh Tram project, the dynamic interaction of concomitant risks must be studied.Design/methodology/approach: A systems dynamic methodology was adopted following the comprehensive literature review. Documentary data were gathered from the case study on Tram Network Project in Edinburgh.Findings: A casual loop of typical evolution of key indicators of risks was then developed. A hypothesised model of social and ecological (SE) risks was derived using the system dynamics (SD) modelling technique. The model was set up following British Standards on risk management to provide a generic tool for risk management in megaproject development. The study reveals that cost and time overruns at the developmental stage of the case project are caused mainly by the effects of interactions of risk factors from the external macro project environment on a timely basis.Originality/value: This article presented a model for simulating the socio-ecological risk confronting the management and construction of megaprojects. The use of SD provided the opportunity to explain the nature of all risks, particularly the SE risks in the past stages of project development.


  • A dynamic system approach to risk analysis for megaproject delivery

    by Zhen Chen, Prince Boateng, Stephen O Ogunlana

    This paper describes a dynamic systems approach to quantitative risk assessment and simulation in megaprojects with regard to social, technical, economic, environmental and political issues relating to sustainability at the construction stage. A literature review was conducted to justify the need for such a dynamic systems approach that originally integrates the functions of two sophisticated quantitative methods – namely, the analytic network process and system dynamics – for an advanced solution to tackle the problems of overruns on budget and schedule at the construction stage in megaproject delivery. The new dynamic systems approach, called SDANP, is described in detail with a theoretical framework and its technical procedure for application. This paper finally provides an experimental case study on the Edinburgh Tram Network project in Scotland to demonstrate the usefulness of the SDANP method, and it also discusses its implementation to support risk management in megaproject delivery towards sustainability.


  • Costing and Technological Challenges of Offshore Oil and Gas Decommissioning in the U.K. North Sea

    by Dominic D. Ahiaga-Dagbui, Peter E. D. Love, Andrew Whyte, Prince Boateng

    A significant number of offshore oil and gas installations in the U.K. North Sea have either exceeded or are approaching the end of their designed economic life. Operators and contractors are confronted with an array of challenges that hinder the cost-effective and safe completion of decommissioning projects. The costing and technological challenges that confront the oil and gas industry are identified using a series of semistructured interviews. One of the most prominent challenges identified was the inability to reliably estimate the volume and cost of work to be undertaken. This is exacerbated by a supply chain with limited capacity and experience in executing decommissioning projects in this fledgling sector in the oil and gas industry. As a result of the analysis that is undertaken, it is recommended that an industrywide decommissioning forum be established to facilitate the sharing of experience and knowledge, particularly with regard to cost information so that operators and contractors can ameliorate the planning and management of the decommissioning process.


  • Open Access

    A dynamic framework for managing the complexities of risks in megaprojects

    by Prince Boateng, Zhen Chen, Stephen O. Ogunlana

    The future of mega infrastructure projects is certain - there will be more risks to manage! The challenge is being met through research and innovation combining current approaches with new. This research adopted a dynamic approach through the combination of Analytical Network Process (ANP) and system dynamics (SD) as an innovative methodology known as SDANP to model complexity in megaprojects design and construction. We communicate how the SDANP model could explore problems caused by Social, Technical, Economic, Environmental and Political (STEEP) risks to construction cost, time and performance and provide insights that lead to organizational learning. We proceed to exemplify by means of a real-life case project in the City of Edinburgh and offer suggestions on what front-ended stakeholders could do to improve the management of risks in megaprojects. The results of the application showed that, when compared to traditional risks assessment methods, this SD model with integrated ANP revealed improvements in managing risks according to STEEP risks criteria. The new framework appears to be a superior solution for solving the dynamic complexities of risks during megaproject design and construction. The findings of the study contribute to the project management theoretical development within the field of megaproject management. Keywords: Analytical Network Process, megaprojects, risk complexity, system dynamics


  • Determinants of outsourcing decision for facilities management (FM) services provision

    by Dubem I. Ikediashi, Stephen O. Ogunlana, Prince Boateng

    Purpose: – This paper aims to examine key determinants that influence the decision to outsource facilities management (FM) services. FM is said to be acquiring increasing popularity all over the globe, with several sourcing strategies springing up for FM services provision.Design/methodology/approach: – Based on questionnaire survey approach, this paper uses purposive sampling to administer 84 questionnaires to selected bank executives operating in the 21 licensed commercial banks in Nigeria, soliciting their responses about what constitute key determinants of outsourcing decision in the context of FM services provision. In all, 41 responses were received, giving a response rate of 49 per cent.Findings: – Supported by empirical evidence, this study established 14 factors as key determinants of outsourcing decision for FM services provision. The top three rated factors were “to improve company’s focus”, “to make cost transparent” and “to improve stakeholders’ satisfaction”, while “to restrict own investment in staff”, “to retire personnel” and “to play along with trend in privatisation” were the least rated. There was no significant difference in the rankings of the factors by respondents, while most of the highly rated factors exhibited strong correlation with other factors.Research limitations/implications: – Due to limited dimension of sample size, more robust techniques such as factor analysis and structural equation modelling could not be used.Originality/value: – This paper provides an enhanced understanding of outsourcing decision and basis for further research into decision support models for outsourcing in the context of FM services provision.


  • Prioritization of Demand Risk Factors in PPP Infrastructure Projects

    by Rajaa Alasad, Ibrahim Motawa, Stephen Ogunlana, Prince Boateng

    Risk management is one of the key success factors of public-private partnerships (PPP) projects. Demand risk, being one of the major risks affecting PPP concessions, needs particular attention and effective management to avoid project failure. Thus, the objective of this study was to identify, rate, and prioritize these factors. The literature provides a list of core factors influencing demand in PPP projects. The full range of factors has been categorized into three groups of user characteristics, facility characteristics, and area characteristics. A questionnaire survey, based on receiving feedbacks from PPP stakeholders, is then used to rate and measure the relative importance of each influencing factor. Since the factors affecting demand risk interact with each other in a complex manner, demand risk identification should involve prioritizing the influencing factors considering their complex interactions. Hence, an analytic network process (ANP)-based technique for prioritizing demand risk factors in the PPP infrastructure concession has been developed. This prioritization process will help identify the most critical factors under each cluster to allow them to be given more attention and be subject to further analysis. The analysis shows that historical experience of paying and willingness to pay are the most important factors under user characteristics cluster, whereas fees of using the facility is most important under facility characteristics cluster, and employment level is most important under area characteristics.