Ranajit Das
Current Organizations / Institutes
The organizations/institutes from the scholar's latest article
Ranajit Das has a total of 5 co-authors. Here are the top co-authors by number of shared publications:
- Elham Mardaneh
Curtin University
3 shared publications - Erkan Topal
Curtin University
3 shared publications Erkan Topal
Mining Engineering, WA School of Mines, Curtin University
2 shared publicationsElham Mardaneh
School of Electrical Engineering, Computing and Mathematical Sciences, Curtin University
1 shared publicationElham Mardenah
Curtin University
1 shared publication
Latest Publications
- Open Access
- 11 March 2024
- Published by Elsevier in Resources Policy
- Vol. 91
Concurrent optimisation of open pit ore and waste movement with optimal haul road selection
- 11 March 2024
- Published by Elsevier in Resources Policy
- Vol. 91
Open AccessConcurrent optimisation of open pit ore and waste movement with optimal haul road selection
- Open Access
- 28 August 2023
- Published by Elsevier in Resources Policy
- Vol. 85
A review of open pit mine and waste dump schedule planning
- 28 August 2023
- Published by Elsevier in Resources Policy
- Vol. 85
Open AccessA review of open pit mine and waste dump schedule planning
- 15 February 2022
- Published by Taylor & Francis in International Journal of Mining, Reclamation and Environment
- Vol. 36 (4) , 287-304
Improved optimised scheduling in stratified deposits in open pit mines – using in-pit dumping
Reducing the footprint of mining by backfilling and rehabilitating open pit mines progressively reduces the amount of land exposed at any point in time. Optimal dump destination (in-pit or external) depends on their availability, which for in-pit is determined by the mined-out void created and available lag distance between the mining face to the dumping face. A mathematical model has been developed to maximise value of the mine while not only considering external dumping option but in-pit dumping as well while maintaining the lag distance with the working face. The model has been applied to a stratified deposit mine with promising results.
- 15 February 2022
- Published by Taylor & Francis in International Journal of Mining, Reclamation and Environment
- Vol. 36 (4) , 287-304
Improved optimised scheduling in stratified deposits in open pit mines – using in-pit dumping
Reducing the footprint of mining by backfilling and rehabilitating open pit mines progressively reduces the amount of land exposed at any point in time. Optimal dump destination (in-pit or external) depends on their availability, which for in-pit is determined by the mined-out void created and available lag distance between the mining face to the dumping face. A mathematical model has been developed to maximise value of the mine while not only considering external dumping option but in-pit dumping as well while maintaining the lag distance with the working face. The model has been applied to a stratified deposit mine with promising results.
- Open Access
- 1 January 2022
- Published by Elsevier in SSRN Electronic Journal
A Review of Open Pit Mine Waste Dump Management Planning
Production sequencing of a mineral deposit, among several constraints, to obtain the best value is a challenging task. Although, there have been numerous researches in this area since the late sixties, is still evolving with newer concepts and methodologies. The key objective in almost all the past research has been the maximisation of NPV (Net Present Value) of a project or to minimise cost or minimise the production deviation from set targets of quality or quantity, with the main focus being on the scheduling of the ore. Considering waste dumps in the production schedule optimisation is a relatively newer concept but an integral part of a mining schedule, which had been omitted in earlier research. This paper reviews the studies on the deterministic and stochastic based models for open-pit production schedule optimisation when waste dump consideration is incorporated into the scheduling. There has been a gradual evolution in the concept of considering waste dumping in mine production schedule from considering ore and waste schedule separately to simultaneous optimisation with the consideration of the waste rock acidity as well as in-pit and ex-pit dumping strategies.
- 1 January 2022
- Published by Elsevier in SSRN Electronic Journal
Open AccessA Review of Open Pit Mine Waste Dump Management Planning
Production sequencing of a mineral deposit, among several constraints, to obtain the best value is a challenging task. Although, there have been numerous researches in this area since the late sixties, is still evolving with newer concepts and methodologies. The key objective in almost all the past research has been the maximisation of NPV (Net Present Value) of a project or to minimise cost or minimise the production deviation from set targets of quality or quantity, with the main focus being on the scheduling of the ore. Considering waste dumps in the production schedule optimisation is a relatively newer concept but an integral part of a mining schedule, which had been omitted in earlier research. This paper reviews the studies on the deterministic and stochastic based models for open-pit production schedule optimisation when waste dump consideration is incorporated into the scheduling. There has been a gradual evolution in the concept of considering waste dumping in mine production schedule from considering ore and waste schedule separately to simultaneous optimisation with the consideration of the waste rock acidity as well as in-pit and ex-pit dumping strategies.
- 30 November 2019
- Published by Springer Nature in Springer Series in Geomechanics and Geoengineering
- p. 33-41
Optimised Pit Scheduling Including In-Pit Dumps for Stratified Deposit
- 30 November 2019
- Published by Springer Nature in Springer Series in Geomechanics and Geoengineering
- p. 33-41
Optimised Pit Scheduling Including In-Pit Dumps for Stratified Deposit