FLORA: New Forensic Schedule Analysis Technique
- 1 July 2008
- journal article
- Published by American Society of Civil Engineers (ASCE) in Journal of Construction Engineering and Management
- Vol. 134 (7) , 483-491
Abstract
While various factors such as float ownership, logic change, and resource allocation (FLORA) affect results of delay analysis, existing delay analysis techniques tend to ignore most if not all of them. To address this insufficiency this paper proposes a new schedule analysis technique called FLORA that simultaneously captures the dynamics of float, logic, and resource allocation in its analyses. FLORA analyzes not only the direct impact of a delay but also its “secondary” effect. The analysis process follows ten rules that are flexible and customizable. A case study is employed to illustrate its application. FLORA yields different and more reasonable outcomes compared to the window analysis technique. Each single analysis may also yield different or even conflicting results. By properly dealing with the current issues of schedule analysis, FLORA can be more reliable. Practitioners may readily accept its analyses and outcomes because they are able to specify, modify, and consent to the rules for schedule a...Keywords
This publication has 20 references indexed in Scilit:
- Preallocation of Total Float in the Application of a Critical Path Method Based Construction ContractJournal of Construction Engineering and Management, 2007
- Selecting a delay analysis method in resolving construction claimsInternational Journal of Project Management, 2006
- Object-Oriented Scheduling for Repetitive Projects with Soft LogicsJournal of Construction Engineering and Management, 2006
- Daily Windows Delay AnalysisJournal of Construction Engineering and Management, 2005
- Development of an object-oriented scheduling model for construction projectsAutomation in Construction, 2003
- Optimization of float use in risk analysis-based network schedulingInternational Journal of Project Management, 1997
- Construction delay analysis techniquesConstruction Management and Economics, 1996
- Total Float Traded as CommodityJournal of Construction Engineering and Management, 1991
- The Development of the Construction Engineer: Past Progress and Future ProblemsJournal of Construction Engineering and Management, 1991
- Sequencing Knowledge for Construction SchedulingJournal of Construction Engineering and Management, 1991