A planning approach for polymetallic mines using a sublevel stoping technique with pillars and ultimate stope limits
Authors:
- 1 July 2019
- journal article
- research article
- Published by Taylor & Francis in Engineering Optimization
- Vol. 52 (6) , 932-944
Abstract
A widely used unsupported underground mining technique is sublevel stoping, in which portions of ore-body within certain size constraints are extracted. In this article, a sequential approach is proposed to solve the sublevel determination problem, which is part of development and infrastructure planning, and the stope layout planning problem for polymetallic sublevel stope mining with pillars. First, a new algorithm is proposed to determine the sublevels, which focuses on minimizing the development costs while maintaining access to the profitable portions of the ore-body. Then, the stope layout is planned between the sublevels. A new mixed-integer linear programming formulation for determining the ultimate stope limits is introduced. A case study is conducted on a copper–molybdenum mine to demonstrate the proposed approaches. The results show that the output of the stope layout plan is within the optimal mining limits, which confirms the validity of the approach.Keywords
Funding Information
- Natural Sciences and Engineering Research Council of Canada (488262-15)
This publication has 18 references indexed in Scilit:
- A new model for open-pit production and waste-dump schedulingEngineering Optimization, 2018
- Multi-objective short-term production scheduling for open-pit mines: a hierarchical decomposition-based algorithmEngineering Optimization, 2018
- Draw rate management system using mathematical programming in extraction sequence optimisation of block cave miningInternational Journal of Mining and Mineral Engineering, 2018
- Strategic mining options optimization: Open pit mining, underground mining or bothInternational Journal of Mining Science and Technology, 2016
- Short-term scheduling of an open-pit mine with multiple objectivesEngineering Optimization, 2016
- Open-pit block sequencing optimization: A mathematical model and solution techniqueEngineering Optimization, 2016
- Underground stope optimization with network flow methodComputers & Geosciences, 2013
- Optimally Locating Additional Drill Holes in Three Dimensions Using Grade and Simulated AnnealingJournal of the Geological Society of India, 2012
- Production planning of mines: Optimisation of block sequencing and destinationInternational Journal of Mining, Reclamation and Environment, 2012
- Incorporating geo-metallurgical information into mine production schedulingJournal of the Operational Research Society, 2011