Andrei Baikalov
Current Organizations / Institutes
The organizations/institutes from the scholar's latest article
Previous Organizations / Institutes
The organizations / institutes from the scholar's other articles in the past ten years
Research Subjects
Research Interests
Andrei Baikalov has a total of 55 co-authors. Here are the top co-authors by number of shared publications:
- Min Liao
ITER Organization, St. Paul Lez Durance, France
3 shared publications - Neil Mitchell
ITER Organization, St. Paul Lez Durance, France
3 shared publications - Alessandro Bonito-Oliva
Fusion for Energy, Barcelona, Spain
2 shared publications - Byung Su Lim
ITER Organization, St. Paul Lez Durance, France
2 shared publications - Fabrice Simon
ITER Organization, St. Paul Lez durance Cedex, France
2 shared publications - Thierry Schild
ITER Organization, St. Paul Lez durance Cedex, France
2 shared publications
Latest Publications
- 13 March 2024
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 34 (5) , 1-5
Acceptance Test of Pre-Compression Rings for ITER Magnet System
In the ITER machine, two sets of three pre-compression rings will be installed at the top and bottom of the 18 toroidal field coil structures. The rings will tightly hold the coils with a radial force of 4,800 t per coil against the operating forces. Four other pre-compression rings will serve as spares. Weighing 3.4 t each, with an inner diameter of 5 m, the rings made of pultruded S-fiberglass composite are possibly the largest and most highly stressed composite structures to be designed for a cryogenic environment. All 10 rings have been delivered to ITER and tested at the ITER pre-compression ring facility at a double nominal stress level. The facility is used to measure the stress at rupture of sub-size rings and for acceptance tests of the full size rings. These tests are supplemented by the stress relaxation test at nominal load on a ring equipped with acoustic sensors, to confirm that the creep performances are also adequate. The paper discuss the design of the rings, the manufacturing route, and the test results including the analysis of the acoustic emission signals.
- 13 March 2024
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 34 (5) , 1-5
Acceptance Test of Pre-Compression Rings for ITER Magnet System
In the ITER machine, two sets of three pre-compression rings will be installed at the top and bottom of the 18 toroidal field coil structures. The rings will tightly hold the coils with a radial force of 4,800 t per coil against the operating forces. Four other pre-compression rings will serve as spares. Weighing 3.4 t each, with an inner diameter of 5 m, the rings made of pultruded S-fiberglass composite are possibly the largest and most highly stressed composite structures to be designed for a cryogenic environment. All 10 rings have been delivered to ITER and tested at the ITER pre-compression ring facility at a double nominal stress level. The facility is used to measure the stress at rupture of sub-size rings and for acceptance tests of the full size rings. These tests are supplemented by the stress relaxation test at nominal load on a ring equipped with acoustic sensors, to confirm that the creep performances are also adequate. The paper discuss the design of the rings, the manufacturing route, and the test results including the analysis of the acoustic emission signals.
- 29 February 2024
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 34 (5) , 1-5
Completion and Factory Acceptance Test of the ITER PF1 Coil
In the International Tokamak Experimental Reactor (ITER), six Poloidal Field (PF) ring coils are employed to initiate, stabilize, and shape the plasma. The Russian Domestic Agency for ITER is responsible for the supply of the PF1 Coil. The manufacturing process, which includes design, tooling procurement, building preparation, and component qualification, spanned over 10 years and concluded in 2022. This article primarily focuses on the final assembly activities following the vacuum pressure impregnation of the coil's winding pack, with specific emphasis on risk mitigation measures to prevent the failure of the coil's electrical insulation and instrumentation. Further, the factory acceptance tests of the completed coil and their outcomes are described and discussed in comparison with the established requirements. These tests include measuring the electrical insulation performance under partial vacuum conditions, checking for leak tightness of the pressurized hydraulic circuit, and conducting dimensional inspections of the coil's interfaces critical for integration into the ITER tokamak. Finally, the article addresses the transportation of the coil and the upcoming cold test to be conducted at the ITER site.
- 29 February 2024
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 34 (5) , 1-5
Completion and Factory Acceptance Test of the ITER PF1 Coil
In the International Tokamak Experimental Reactor (ITER), six Poloidal Field (PF) ring coils are employed to initiate, stabilize, and shape the plasma. The Russian Domestic Agency for ITER is responsible for the supply of the PF1 Coil. The manufacturing process, which includes design, tooling procurement, building preparation, and component qualification, spanned over 10 years and concluded in 2022. This article primarily focuses on the final assembly activities following the vacuum pressure impregnation of the coil's winding pack, with specific emphasis on risk mitigation measures to prevent the failure of the coil's electrical insulation and instrumentation. Further, the factory acceptance tests of the completed coil and their outcomes are described and discussed in comparison with the established requirements. These tests include measuring the electrical insulation performance under partial vacuum conditions, checking for leak tightness of the pressurized hydraulic circuit, and conducting dimensional inspections of the coil's interfaces critical for integration into the ITER tokamak. Finally, the article addresses the transportation of the coil and the upcoming cold test to be conducted at the ITER site.
- 15 February 2024
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 34 (5) , 1-5
Delivered Poloidal Field Coils to ITER Fusion Tokamak Facility: Status, Factory Acceptance Test Results and Overview of the Undergone Electrical Tests in Manufacturing Processes
Fusion for Energy (F4E), the European Domestic Agency for the International Thermonuclear Experimental Reactor (ITER) is responsible for the manufacturing, test and delivery of 5 out of 6 Poloidal Field Coils of ITER. F4E has currently delivered 4 coils: PF2, PF4, PF5 and PF6, the last two are installed in the Tokamak pit in temporary positions while PF2 and PF4 are stored awaiting the Tokamak torus completion. At the PF coils manufacturing production site in Cadarache, France, few meters away from the ITER Tokamak assembly building, F4E is currently finalizing the manufacturing and testing of the largest coil: PF3, with 24 m diameter and a weight of 384 t, approaching to the end of an endeavor that started back in 2013. This article describes all electrical tests the PF coils underwent to meet the ITER technical requirements during their lengthy manufacturing process, and which lasted several years. Tests performed at key points of the manufacturing process avoided discovering non-conformities at later stages that could otherwise become critical for the project accomplition. The main electrical tests consisted of high voltage DC/AC, partial discharge tests, and local and global Paschen tests. The experimental setups and procedures are presented and discussed in more detail. We also summarize the acceptance test results for the finalized coils i.e., 80 K forced flow pressure drop testing, leak tightness in vacuum before, during and after the thermal cycle to 80 K.
- 15 February 2024
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 34 (5) , 1-5
Delivered Poloidal Field Coils to ITER Fusion Tokamak Facility: Status, Factory Acceptance Test Results and Overview of the Undergone Electrical Tests in Manufacturing Processes
Fusion for Energy (F4E), the European Domestic Agency for the International Thermonuclear Experimental Reactor (ITER) is responsible for the manufacturing, test and delivery of 5 out of 6 Poloidal Field Coils of ITER. F4E has currently delivered 4 coils: PF2, PF4, PF5 and PF6, the last two are installed in the Tokamak pit in temporary positions while PF2 and PF4 are stored awaiting the Tokamak torus completion. At the PF coils manufacturing production site in Cadarache, France, few meters away from the ITER Tokamak assembly building, F4E is currently finalizing the manufacturing and testing of the largest coil: PF3, with 24 m diameter and a weight of 384 t, approaching to the end of an endeavor that started back in 2013. This article describes all electrical tests the PF coils underwent to meet the ITER technical requirements during their lengthy manufacturing process, and which lasted several years. Tests performed at key points of the manufacturing process avoided discovering non-conformities at later stages that could otherwise become critical for the project accomplition. The main electrical tests consisted of high voltage DC/AC, partial discharge tests, and local and global Paschen tests. The experimental setups and procedures are presented and discussed in more detail. We also summarize the acceptance test results for the finalized coils i.e., 80 K forced flow pressure drop testing, leak tightness in vacuum before, during and after the thermal cycle to 80 K.
- 8 January 2024
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 34 (5) , 1-5
Manufacturing and Assembly of the ITER Correction Coils
The ITER Correction Coils (CC) system consists of 3 sets of 6 coils each: Bottom (BCC), Side (SCC) and Top (TCC) Correction Coils. The ITER CC are supplied in-kind by the Chinese Domestic Agencies (CNDA) and the construction is carried out by Chinese Academy of Science Institute ASIPP. The 6 BCC and TCC have been delivered to the ITER Organization. Whereas BCC and TCC are planar coils, SCC are wound on a cylinder and require a completely different line of manufacturing. The SCC are at different stages of the last manufacturing processes, between the assembly of the terminal service box (TSB) and Final Acceptance Tests (FAT). This paper presents the manufacturing process, which involves manufacturing of multi-layer winding of non-circular shape, insertion into a stainless steel case, closed by a powerful 20 kW laser weld, in the vicinity of the CC superconductor insulation. The reliability of the manufacturing processes to manage winding/insulation/welding were essential for achieving the final quality and tolerances of few mm of these 7 m long coils. Some lessons learnt during the CC production components and subsequent work execution will be detailed. The BCC are placed in the ITER tokamak Pit, where they will stay for several years until attachment onto the Toroidal Fields coils (TF). A description of the assembly process for BCC and SCC will be introduced.
- 8 January 2024
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 34 (5) , 1-5
Manufacturing and Assembly of the ITER Correction Coils
The ITER Correction Coils (CC) system consists of 3 sets of 6 coils each: Bottom (BCC), Side (SCC) and Top (TCC) Correction Coils. The ITER CC are supplied in-kind by the Chinese Domestic Agencies (CNDA) and the construction is carried out by Chinese Academy of Science Institute ASIPP. The 6 BCC and TCC have been delivered to the ITER Organization. Whereas BCC and TCC are planar coils, SCC are wound on a cylinder and require a completely different line of manufacturing. The SCC are at different stages of the last manufacturing processes, between the assembly of the terminal service box (TSB) and Final Acceptance Tests (FAT). This paper presents the manufacturing process, which involves manufacturing of multi-layer winding of non-circular shape, insertion into a stainless steel case, closed by a powerful 20 kW laser weld, in the vicinity of the CC superconductor insulation. The reliability of the manufacturing processes to manage winding/insulation/welding were essential for achieving the final quality and tolerances of few mm of these 7 m long coils. Some lessons learnt during the CC production components and subsequent work execution will be detailed. The BCC are placed in the ITER tokamak Pit, where they will stay for several years until attachment onto the Toroidal Fields coils (TF). A description of the assembly process for BCC and SCC will be introduced.
- Open Access
- 20 June 2002
- Published by American Physical Society (APS) in Physical Review B
- Vol. 66 (1) , 014503
Superconductivity, intragrain penetration depth, and Meissner effect ofThe hole concentration the transition temperature the intragrain penetration depth and the Meissner effect were measured for annealed samples. The intragrain superconducting transition temperature varied from 17 to 40 K while the p changed by only The intragrain superfluid density and the diamagnetic drop of the field-cooled magnetization across (the Meissner effect), however, increased more than 10 times. All of these findings are in disagreement with both the vs p and the vs correlations proposed for homogeneous cuprates, but are in line with a possible phase separation and the granularity associated with it.- 20 June 2002
- Published by American Physical Society (APS) in Physical Review B
- Vol. 66 (1) , 014503
Open AccessSuperconductivity, intragrain penetration depth, and Meissner effect ofThe hole concentration the transition temperature the intragrain penetration depth and the Meissner effect were measured for annealed samples. The intragrain superconducting transition temperature varied from 17 to 40 K while the p changed by only The intragrain superfluid density and the diamagnetic drop of the field-cooled magnetization across (the Meissner effect), however, increased more than 10 times. All of these findings are in disagreement with both the vs p and the vs correlations proposed for homogeneous cuprates, but are in line with a possible phase separation and the granularity associated with it.