Analysis of the impacts of slope angle variation on slope stability and NPV via two different final pit definition techniques
Authors:
- Leonardo Soares ChavesLCLeonardo Soares Chaves
- Luiz Alberto CarvalhoLCLuiz Alberto Carvalho
- Felipe Ribeiro SouzaFSFelipe Ribeiro Souza
- Beck NaderBNBeck Nader
- Carlos Enrique Arroyo OrtizCOCarlos Enrique Arroyo Ortiz
- Vidal Félix Navarro TorresVTVidal Félix Navarro Torres
- Taís Renata CâmaraTCTaís Renata Câmara
- Gian Franco Napa-GarcíaGNGian Franco Napa-García
- George Eduardo Sales ValadãoGVGeorge Eduardo Sales Valadão
Open Access
- 1 March 2020
- journal article
- mining
- Published by FapUNIFESP (SciELO) in REM - International Engineering Journal
- Vol. 73 (1) , 119-126
Abstract
The traditionally and widely used Lerchs-Grossmann algorithm presents well-known limitations that newer propositions attempt to overcome. The direct block schedule (DBS) methodology, which has gained relevance with computational advances, obtains the final pit as a natural result of production sequencing, different from Lerchs-Grossmann-based algorithms. This process flow applies constraints in the final pit definition stage attempting to provide a more realistic result and to minimize risks. Slope instability is a common and inherent risk to open pit mining and may affect the project's net present value (NPV). A study of the impacts of slope angle variations on safety indexes and final pit NPV provides an auxiliary tool for the overall slope angle definition process. This article presents a case study in which the effects of variations of the overall slope angle on the safety factor (SF) and project NPV were analyzed. A total of 25 pits were generated by each studied final pit definition methodology, and each pit had the sections with the varied slope angles analyzed in the stability assessment, resulting in a total of 150 slopes analyzed. A comparison between the results obtained by the two different methodologies implemented in commercial software is presented. The results show no relationship between the NPV and the overall slope angle using the DBS methodology. An analysis of the results for each geotechnical sector obtained by the traditional methodology was conducted and may contribute to the trade-off analysis between the best slope angle to achieve a reasonable SF and the maximum NPV.Keywords
This publication has 14 references indexed in Scilit:
- Impact of grade distribution on the final pit limit definitionREM - International Engineering Journal, 2018
- Direct block scheduling under marketing uncertaintiesREM - International Engineering Journal, 2018
- Comparison between the application of the conventional mine planning and of the direct block scheduling on an open pit mine ProjectREM - International Engineering Journal, 2018
- Application of optimized models through direct block scheduling in traditional mine planningJournal of the Southern African Institute of Mining and Metallurgy, 2018
- Governing risk elements through open pit slope optimizationJournal of the Southern African Institute of Mining and Metallurgy, 2018
- Open pit mine planning considering geomechanical fundamentalsInternational Journal of Mining, Reclamation and Environment, 2017
- Design and implementation of steeper slope angles on a kimberlite open pit diamond operation-a practical approachJournal of the Southern African Institute of Mining and Metallurgy, 2016
- Stochastic long-term production scheduling of iron ore deposits: Integrating joint multi-element geological uncertaintyJournal of Mining Science, 2013
- The new Fundamental Tree Algorithm for production scheduling of open pit minesEuropean Journal of Operational Research, 2007
- Mechanical Tests on Pervasively Jointed Rock Material: Insight into Rock Mass BehaviourRock Mechanics and Rock Engineering, 2000