SPSteve Patlan

Steve Patlan

*This is an algorithmically generated author record based on publicly available information.

Current Organizations / Institutes

The organizations/institutes from the scholar's latest article


Steve Patlan has a total of 14 co-authors. Here are the top co-authors by number of shared publications:


Latest Publications

  • 4.5 K Paschen Qualification Testing of Terminal Joint and Voltage Tap Insulation Designs for ITER CS Module Test Facility

    by Bryce Fledderman, Kenneth Khumthong, Nikolai Norausky, Edward Ortiz, John Smith, Steve Patlan, Nicolai Martovetsky, Alan Langhorn

    General Atomics (GA) is fabricating seven ITER Central Solenoid Modules (CSM) for the ITER Organization (IO). As part of the fabrication process, all CSMs undergo factory acceptance testing (FAT) prior to shipment to the IO. The FAT includes charging the modules to 40 kA and performing fast discharges (7.3 second decay time constant) to measure alternating current (AC) losses. These fast discharges generate high voltages at the electrical connections between the CSM and the test facility. Due to a fast discharge fault during the CSM 3 FAT, Paschenization methods of high voltage connections between the CSM and the test facility needed to be developed, qualified, and implemented. These connections included the coaxial and twinbox joints, all in-chamber instrumentation voltage tap wire splices, and voltage tap chamber feedthroughs. A test article was manufactured to replicate these connections and joints, and qualify the locally removable Paschenized insulation designs with a Paschen Test at 4.5 K. The 4.5 K Paschen test was comprised of 15 kV tests between 1E-03 and 1 mbar. This paper will present and discuss the Paschenization methods, lessons learned from research, and the CSM implementation in the test facility.


  • ITER CS Module Test Facility Operational Lessons From CS Modules 1–4

    by Kenneth Khumthong, Edward Ortiz, Jeffery Sheeron, Bryce Fledderman, Nikolai Norausky, John Smith, Steve Patlan, Nicolai Martovetsky, Kevin Freudenberg, Graham Rossano, et al.

    General Atomics (GA) is under contract to UT-Battelle c/o Oak Ridge National Laboratory for the fabrication of ITER Central Solenoid Modules (CSM). GA will provide seven modules to ITER Organization (IO), six of which will be assembled in a stack that forms the ITER Central Solenoid. All CSMs are required to pass factory acceptance testing (FAT) at General Atomics’ Magnet Technology Center (MTC) test facility prior to shipment to IO. Currently, CSMs 1, 2, and 4 have completed FAT and have been delivered to IO. CSM5 has completed FAT and CSM3 will repeat FAT after resuming its test campaign. FATs on CSMs 6 and 7 are planned as the modules complete fabrication. The MTC test facility was designed and built to conduct CSM factory acceptance tests. The test facility consists of the test chamber, high vacuum system, 4.5 K recirculating supercritical helium refrigeration plant, 50 kA DC power supply, capacitor-pulsed DC circuit breakers, 1 GJ discharge resistor, high-temperature superconducting current feeders, data acquisition system, supervisory control and magnet quench protection system, and a multitude of supporting equipment. Where possible, the test facility utilizes similar equipment planned for use at IO for magnet operation. The test facility operational lessons learned as a result of CSM 1–4 FATs are presented and discussed in this paper.