Nikolai Norausky
Current Organizations / Institutes
The organizations/institutes from the scholar's latest article
Research Subjects
Research Interests
Nikolai Norausky has a total of 49 co-authors. Here are the top co-authors by number of shared publications:
- Nicolai Martovetsky
US ITER Project, Oak Ridge National Laboratory, Oak Ridge, TN, USA
7 shared publications - John Smith
General Atomics, San Diego, CA, USA
6 shared publications - Kenneth Khumthong
General Atomics, San Diego, CA, USA
6 shared publications - Edward Ortiz
General Atomics, San Diego, CA, USA
5 shared publications - Thierry Schild
ITER Organization, St. Paul Lez durance Cedex, France
5 shared publications - Yasuyuki Miyoshi
ITER Organization, St. Paul Lez durance Cedex, France
5 shared publications
Latest Publications
- 24 November 2025
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 36 (3) , 1-7
ITER Central Solenoid Manufacturing and Assembly Progress
ITER Central Solenoid (CS) system manufacturing, after ten years, completed all coil modules manufacturing and testing to full current 40 kA at 4.5 K. Meanwhile the assembly work at ITER has progressed steadily since its start five years ago. A summary of characteristic technical challenges found in manufacturing and assembly, and an outlook of what is expected towards the completion of CS assembly are presented.
- 24 November 2025
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 36 (3) , 1-7
ITER Central Solenoid Manufacturing and Assembly Progress
ITER Central Solenoid (CS) system manufacturing, after ten years, completed all coil modules manufacturing and testing to full current 40 kA at 4.5 K. Meanwhile the assembly work at ITER has progressed steadily since its start five years ago. A summary of characteristic technical challenges found in manufacturing and assembly, and an outlook of what is expected towards the completion of CS assembly are presented.
- 29 October 2025
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 36 (3) , 1-4
Recovery of Terminations in ITER CS Module 3
The ITER Central Solenoid (CS) is under fabrication by the US ITER organization and its subcontractors. All CS modules (CSM) were or will be tested at 40 kA in the Final Test facility at General Atomics. CSM 3 testing campaign took place in 2021, and a breakdown occurred that damaged the terminations of the module. To recover, new terminations needed to be designed, qualified and built to make the CSM3 fit for service. This effort had several challenges that were not addressed in the previous projects with large Nb3Sn magnets with cable-in-conduit conductors. This paper describes a design, fabrication and qualification of the terminations.
- 29 October 2025
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 36 (3) , 1-4
Recovery of Terminations in ITER CS Module 3
The ITER Central Solenoid (CS) is under fabrication by the US ITER organization and its subcontractors. All CS modules (CSM) were or will be tested at 40 kA in the Final Test facility at General Atomics. CSM 3 testing campaign took place in 2021, and a breakdown occurred that damaged the terminations of the module. To recover, new terminations needed to be designed, qualified and built to make the CSM3 fit for service. This effort had several challenges that were not addressed in the previous projects with large Nb3Sn magnets with cable-in-conduit conductors. This paper describes a design, fabrication and qualification of the terminations.
- 20 January 2025
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 35 (5) , 1-4
Continuing Testing of the ITER CS Modules
The ITER Central Solenoid (CS) is under fabrication by the US ITER organization and its subcontractors. US ITER will supply seven modules to ITER IO, six of which will be assembled in a stack that forms the ITER Central Solenoid. All CS modules (CSM) were or will be tested at 40 kA in the Final Test facility at General Atomics (GA). CSM 5, 6, and 7 were tested in 2023 and 2024. Some instrumentation was updated to obtain information on the suppression of the inductive noise in the CSMs at high dB/dt events, which will lead to improved quench detection and protection of the modules. All the standard tests performed on previous CSMs to validate the properties of the CSM have also been performed on CSMs 5-7 to confirm the consistency of the CSM properties for ITER CS. The Tcs margin demonstration was done for the first time at the GA Facility on CSM6. Test results and analysis are presented and discussed.
- 20 January 2025
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 35 (5) , 1-4
Continuing Testing of the ITER CS Modules
The ITER Central Solenoid (CS) is under fabrication by the US ITER organization and its subcontractors. US ITER will supply seven modules to ITER IO, six of which will be assembled in a stack that forms the ITER Central Solenoid. All CS modules (CSM) were or will be tested at 40 kA in the Final Test facility at General Atomics (GA). CSM 5, 6, and 7 were tested in 2023 and 2024. Some instrumentation was updated to obtain information on the suppression of the inductive noise in the CSMs at high dB/dt events, which will lead to improved quench detection and protection of the modules. All the standard tests performed on previous CSMs to validate the properties of the CSM have also been performed on CSMs 5-7 to confirm the consistency of the CSM properties for ITER CS. The Tcs margin demonstration was done for the first time at the GA Facility on CSM6. Test results and analysis are presented and discussed.
- 5 March 2024
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 34 (5) , 1-5
Selected Topics of Technical Challenges of the ITER Central Solenoid
Central Solenoid (CS) components have an abundance of technical challenges ranging from material science to component interfacing. In manufacturing, a CS module is subjected to stringent high voltage insulation strength tests at multiple occasions. The engineering challenge is where a multitude of quench detection wires need to exit the bulk insulation and the materials boundary or compatibility become an issue. In assembly, each CS module terminals is jumped to its respective feeder line via an extension lead that is manufactured with interfacing constraints with the module terminal vector as well as the feeder terminal mating surface. Another critical aspect is the clearance available in assembly with other surrounding tokamak components. A summary of the issues found in manufacturing of large scale structural components is also given.
- 5 March 2024
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 34 (5) , 1-5
Selected Topics of Technical Challenges of the ITER Central Solenoid
Central Solenoid (CS) components have an abundance of technical challenges ranging from material science to component interfacing. In manufacturing, a CS module is subjected to stringent high voltage insulation strength tests at multiple occasions. The engineering challenge is where a multitude of quench detection wires need to exit the bulk insulation and the materials boundary or compatibility become an issue. In assembly, each CS module terminals is jumped to its respective feeder line via an extension lead that is manufactured with interfacing constraints with the module terminal vector as well as the feeder terminal mating surface. Another critical aspect is the clearance available in assembly with other surrounding tokamak components. A summary of the issues found in manufacturing of large scale structural components is also given.
- 29 January 2024
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 34 (5) , 1-6
Progress of ITER Central Solenoid Assembly
This paper describes critical assembly process qualifications, acceptance criteria, and worker training of ITER Central Solenoid Assembly. Coaxial joint assembly was qualified and trained to achieve resistance below 4.1 nOhm. The electrical insulation process was qualified to 30 kV and 15 kV under Paschen conditions. Shear pin drilling and installation within specified tolerance was achieved. Modules were lifted and positioned within 2 mm. The lessons learned, and subsequent work execution onsite within the IO facility assembly hall are also presented.
- 29 January 2024
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 34 (5) , 1-6
Progress of ITER Central Solenoid Assembly
This paper describes critical assembly process qualifications, acceptance criteria, and worker training of ITER Central Solenoid Assembly. Coaxial joint assembly was qualified and trained to achieve resistance below 4.1 nOhm. The electrical insulation process was qualified to 30 kV and 15 kV under Paschen conditions. Shear pin drilling and installation within specified tolerance was achieved. Modules were lifted and positioned within 2 mm. The lessons learned, and subsequent work execution onsite within the IO facility assembly hall are also presented.
- 23 January 2024
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 34 (5) , 1-4
4.5 K Paschen Qualification Testing of Terminal Joint and Voltage Tap Insulation Designs for ITER CS Module Test Facility
General Atomics (GA) is fabricating seven ITER Central Solenoid Modules (CSM) for the ITER Organization (IO). As part of the fabrication process, all CSMs undergo factory acceptance testing (FAT) prior to shipment to the IO. The FAT includes charging the modules to 40 kA and performing fast discharges (7.3 second decay time constant) to measure alternating current (AC) losses. These fast discharges generate high voltages at the electrical connections between the CSM and the test facility. Due to a fast discharge fault during the CSM 3 FAT, Paschenization methods of high voltage connections between the CSM and the test facility needed to be developed, qualified, and implemented. These connections included the coaxial and twinbox joints, all in-chamber instrumentation voltage tap wire splices, and voltage tap chamber feedthroughs. A test article was manufactured to replicate these connections and joints, and qualify the locally removable Paschenized insulation designs with a Paschen Test at 4.5 K. The 4.5 K Paschen test was comprised of 15 kV tests between 1E-03 and 1 mbar. This paper will present and discuss the Paschenization methods, lessons learned from research, and the CSM implementation in the test facility.
- 23 January 2024
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 34 (5) , 1-4
4.5 K Paschen Qualification Testing of Terminal Joint and Voltage Tap Insulation Designs for ITER CS Module Test Facility
General Atomics (GA) is fabricating seven ITER Central Solenoid Modules (CSM) for the ITER Organization (IO). As part of the fabrication process, all CSMs undergo factory acceptance testing (FAT) prior to shipment to the IO. The FAT includes charging the modules to 40 kA and performing fast discharges (7.3 second decay time constant) to measure alternating current (AC) losses. These fast discharges generate high voltages at the electrical connections between the CSM and the test facility. Due to a fast discharge fault during the CSM 3 FAT, Paschenization methods of high voltage connections between the CSM and the test facility needed to be developed, qualified, and implemented. These connections included the coaxial and twinbox joints, all in-chamber instrumentation voltage tap wire splices, and voltage tap chamber feedthroughs. A test article was manufactured to replicate these connections and joints, and qualify the locally removable Paschenized insulation designs with a Paschen Test at 4.5 K. The 4.5 K Paschen test was comprised of 15 kV tests between 1E-03 and 1 mbar. This paper will present and discuss the Paschenization methods, lessons learned from research, and the CSM implementation in the test facility.
- 13 December 2023
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 34 (5) , 1-6
ITER CS Module Test Facility Operational Lessons From CS Modules 1–4
General Atomics (GA) is under contract to UT-Battelle c/o Oak Ridge National Laboratory for the fabrication of ITER Central Solenoid Modules (CSM). GA will provide seven modules to ITER Organization (IO), six of which will be assembled in a stack that forms the ITER Central Solenoid. All CSMs are required to pass factory acceptance testing (FAT) at General Atomics’ Magnet Technology Center (MTC) test facility prior to shipment to IO. Currently, CSMs 1, 2, and 4 have completed FAT and have been delivered to IO. CSM5 has completed FAT and CSM3 will repeat FAT after resuming its test campaign. FATs on CSMs 6 and 7 are planned as the modules complete fabrication. The MTC test facility was designed and built to conduct CSM factory acceptance tests. The test facility consists of the test chamber, high vacuum system, 4.5 K recirculating supercritical helium refrigeration plant, 50 kA DC power supply, capacitor-pulsed DC circuit breakers, 1 GJ discharge resistor, high-temperature superconducting current feeders, data acquisition system, supervisory control and magnet quench protection system, and a multitude of supporting equipment. Where possible, the test facility utilizes similar equipment planned for use at IO for magnet operation. The test facility operational lessons learned as a result of CSM 1–4 FATs are presented and discussed in this paper.
- 13 December 2023
- Published by Institute of Electrical and Electronics Engineers (IEEE) in IEEE Transactions on Applied Superconductivity
- Vol. 34 (5) , 1-6
ITER CS Module Test Facility Operational Lessons From CS Modules 1–4
General Atomics (GA) is under contract to UT-Battelle c/o Oak Ridge National Laboratory for the fabrication of ITER Central Solenoid Modules (CSM). GA will provide seven modules to ITER Organization (IO), six of which will be assembled in a stack that forms the ITER Central Solenoid. All CSMs are required to pass factory acceptance testing (FAT) at General Atomics’ Magnet Technology Center (MTC) test facility prior to shipment to IO. Currently, CSMs 1, 2, and 4 have completed FAT and have been delivered to IO. CSM5 has completed FAT and CSM3 will repeat FAT after resuming its test campaign. FATs on CSMs 6 and 7 are planned as the modules complete fabrication. The MTC test facility was designed and built to conduct CSM factory acceptance tests. The test facility consists of the test chamber, high vacuum system, 4.5 K recirculating supercritical helium refrigeration plant, 50 kA DC power supply, capacitor-pulsed DC circuit breakers, 1 GJ discharge resistor, high-temperature superconducting current feeders, data acquisition system, supervisory control and magnet quench protection system, and a multitude of supporting equipment. Where possible, the test facility utilizes similar equipment planned for use at IO for magnet operation. The test facility operational lessons learned as a result of CSM 1–4 FATs are presented and discussed in this paper.